Concrete is ordered by volume, in cubic yards or cubic metres. Working out the volume of a slab is a simple length-times-width-times-thickness...
Concrete is ordered by volume, in cubic yards or cubic metres. Working out the volume of a slab is a simple length-times-width-times-thickness calculation, with one unit conversion at the end.
Measure the length and width in feet and the thickness in inches, then convert the thickness to feet by dividing by 12. A slab 10 ft by 12 ft and 4 inches thick is 10 times 12 times (4 divided by 12), which is 40 cubic feet. Divide by 27 to get cubic yards: 40 divided by 27 is about 1.48 cubic yards. Order about 10 percent extra for waste and uneven ground, so about 1.63 cubic yards, and round up to the nearest quarter yard.
For a slab in metres, multiply length by width by thickness in metres to get cubic metres directly. A 3 m by 4 m slab, 0.1 m thick, is 1.2 cubic metres.
A driveway is 20 ft by 10 ft and 6 inches thick. The volume is 20 times 10 times 0.5, which is 100 cubic feet, or 100 divided by 27, which is about 3.70 cubic yards. With 10 percent extra, order about 4.07 cubic yards.
The most common error is forgetting to convert inches to feet. Four inches is one third of a foot, not 4 feet.
How many cubic yards of concrete does a 12 ft by 12 ft slab, 4 inches thick, need? (Answer: 48 cubic feet, about 1.78 cubic yards.)
If the numbers look surprising, recheck the inputs before doubting the method. A room measured in inches instead of feet, or a rate typed in as a percent instead of a decimal, will throw the answer off by a large factor. A quick estimate first tells you roughly what to expect.
What if the measurements change? The formula does not, so measure again and run the same steps. A careful second measurement is the cheapest insurance against buying the wrong amount.